Section 4 - CNC Machine Operation - 23Microrouter CNC Machine User's Manual
4: Using your Microrouter - Overview
Several steps must be completed before the final manufacture of a
part. The flowchart below lists the general steps that should be
followed for CNC file creation, simulation and final part manufacture, in
the recommended order. However, miscellaneous factors may warrant
the user to complete the steps in a different order to that shown.
For more detailed
information regarding
these steps please refer
to your separate CNC
Machine Control
Software User's
Manual.
Note *
-
x
Steps F and G are not
required when working
with a simulated CNC
machine (for example,
Virtual Reality).
Billet data is taken from
Denford directives
written in the CNC
program - step B.
Tooling data is taken
from the configuration of
the software tooling -
step C.
Note
-
x
B: Load or create the CNC program
(see Note * left)
D: Simulate the CNC program in 2D or 3D
(see Note * left)
E: Establish communications and home the Microrouter
(see Note * left)
F: Prepare any tooling hardware for the Microrouter
(see section 5: pages 32 to 39)
G: Load the billet into the Microrouter
(see section 6: pages 40 to 47)
H: Configure the workpiece offset file and tool length offsets
(see Note * left)
C: Configure the tooling files in theCNC Control Software
(see Note * left)
I: Manufacture the part
(see section 4: pages 29 to 31 and see Note * left)
A: Switch on the Microrouter, then start the CNC Control Software
(see section 4: pages 27 to 28 and see Note * left)